Leaves on the Line

Cricklewood

CRI East Midlands route
CSV JSON

6 delay minutes

Most of the delay picked up at Cricklewood in the four weeks to 9 December 2023 came from other operator causes.

0% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%1
Weather and structures--7%1
Autumn--7%-
External--4%-
Network management--17%-
The operators' causes
Train faults--16%-
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other6100%7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
V8Train striking or being struck by a bird6
Since 2018
CodeWhat Network Rail loggedMinutes
XLFire external to but directly affecting the network (incl. line blocks for emergency services attending off network incidents)27
I6Delays as a result of line blocks / track patrols (including late handback)26
XMExternal utility incident including gas, water mains, overhead power lines25
TITraincrew rostering problem19
JLSafety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff)17
M8Technical failures above the Solebar12
TZOther Passenger Train Operating Company causes10
TGDriver10
IRBroken/cracked/twisted/buckled/flawed rail10
R3Station Staff unavailable - missing or uncovered10