Leaves on the Line

Cosham

CSA Wessex route
CSV JSON

1,023 delay minutes

The biggest share (37%) of the delay picked up at Cosham in the four weeks to 9 December 2023 came from signal, points and power faults.

54% of these minutes were knock-on from something that happened elsewhere first. 98% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track20320%8% 7 a day, the most in 5 years-
Signals, points and power37737%16% 13 a day, the most in 5 years-
Weather and structures10<1%7% 0 a day, more than 3 of the other 4 years-
Autumn182%7% 1 a day, the most in 5 years-
External10<1%4% 0 a day, the least in 5 years-
Network management14214%17% 5 a day, more than 1 of the other 4 years-
The operators' causes
Train faults13813%16% 5 a day, more than 3 of the other 4 years-
Traincrew515%11% 2 a day, the least in 5 years-
Stations353%3% 1 a day, the most in 5 years-
Operations303%5% 1 a day, the most in 5 years-
Operator, other10<1%7% 0 a day, the least in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
IBPoints failure (including no fault found)205
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.199
IISignalling lineside cable fault117
MFEngineering non-technical delays associated with Engineering staff who are not based in an Engineering depot e.g. Cleaners60
I5Possession over-run from planned work50
TGDriver42
MDTechnical failures below the solebar28
RQUn-booked assistance for a person with reduced mobility joining/alighting,28
TZOther Passenger Train Operating Company causes22
J3Axle Counter Failure21
Since 2018
CodeWhat Network Rail loggedMinutes
IISignalling lineside cable fault2,985
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.2,198
TGDriver1,947
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure1,657
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)1,456
J3Axle Counter Failure1,258
ICTrack circuit failure (including no fault found)1,157
MDTechnical failures below the solebar1,119
IBPoints failure (including no fault found)1,067
JXMiscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains)1,060