Leaves on the Line

City Thameslink

CTK Kent route
CSV JSON

17 delay minutes

Most of the delay picked up at City Thameslink in the four weeks to 9 December 2023 came from traincrew problems.

0% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures--7%-
Autumn--7%-
External--4%-
Network management--17%-
The operators' causes
Train faults--16%-
Traincrew17100%11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
TGDriver17
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver78
TITraincrew rostering problem45
X8Animal Strike or incursion not within the control of Network Rail33
TBTrain cancelled or delayed at Train Operators request30
XOExternal trees, building or structures encroaching or falling onto network infrastructure (not weather or vandalism)30
J3Axle Counter Failure29
M8Technical failures above the Solebar27
I5Possession over-run from planned work25
XLFire external to but directly affecting the network (incl. line blocks for emergency services attending off network incidents)22
ICTrack circuit failure (including no fault found)21