Leaves on the Line

Denby Dale

DBD North & East route
CSV JSON

0 delay minutes

No delay was picked up at Denby Dale in the four weeks to 9 December 2023.

100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures--7%-
Autumn--7%-
External--4%-
Network management--17%-
The operators' causes
Train faults--16%-
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
Nothing logged.
Since 2018
CodeWhat Network Rail loggedMinutes
RZOther Station Operating causes13
XNRoad or crossing related incidents inc. cars on line, crossing misuse and priority to emergency services (NOT bridge strikes)6
IHPower Supply And Distribution System Failure6
T8Delays at Station believed to be operator cause and Information required from operator (Ops responsibility)6
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure5
J0Telecom equipment radio failure (GSM-R)3