Leaves on the Line

Derby Road (Ipswich)

DBR Anglia route
CSV JSON

237 delay minutes

The biggest share (31%) of the delay picked up at Derby Road (Ipswich) in the four weeks to 9 December 2023 came from other operator causes.

81% of these minutes were knock-on from something that happened elsewhere first. 96% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track2912%8% 1 a day, more than 3 of the other 4 years-
Signals, points and power3515%16% 1 a day, more than 3 of the other 4 years-
Weather and structures63%7% 0 a day, more than 2 of the other 4 years-
Autumn31%7% 0 a day, more than 2 of the other 4 years-
External52%4% 0 a day, more than 2 of the other 4 years-
Network management4519%17% 2 a day, more than 3 of the other 4 years-
The operators' causes
Train faults2812%16% 1 a day, more than 1 of the other 4 years-
Traincrew42%11% 0 a day, more than 1 of the other 4 years-
Stations--3% 0 a day, the least in 5 years-
Operations94%5% 0 a day, the least in 5 years-
Operator, other7431%7% 3 a day, more than 2 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 5 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
ACWaiting Train preparation or completion of TOPS list/RT397339
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.29
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure26
FWLate start/yard overtime not explained by Operator19
M0Confirmed train cab based safety system fault (including GSMR)14
OCSignaller including mis-routing (not ERTM /ETCS related)12
OBDelayed by signaller not applying applicable regulating policy10
QMTrain schedule/STP Process including erroneous simplifiers10
FHFOC Planning issue (not diagramming or rostering)9
MUDepot operating problem9
Since 2018
CodeWhat Network Rail loggedMinutes
ACWaiting Train preparation or completion of TOPS list/RT39731,034
FWLate start/yard overtime not explained by Operator840
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.722
MUDepot operating problem691
MCDiesel Loco failure, defect, attention651
JLSafety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff)581
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles395
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure357
QMTrain schedule/STP Process including erroneous simplifiers335
AECongestion in off Network Rail network Terminal or Yard331