Deal
680 delay minutes
The biggest share (20%) of the delay picked up at Deal in the four weeks to 9 December 2023 came from other operator causes.
50% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 6 | <1% | 8% | 0 a day, more than 1 of the other 4 years | - |
| Signals, points and power | 66 | 10% | 16% | 2 a day, more than 1 of the other 4 years | - |
| Weather and structures | 132 | 19% | 7% | 5 a day, the most in 5 years | - |
| Autumn | 123 | 18% | 7% | 4 a day, more than 2 of the other 4 years | - |
| External | - | - | 4% | 0 a day, the least in 5 years | - |
| Network management | 101 | 15% | 17% | 4 a day, more than 3 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 75 | 11% | 16% | 3 a day, the most in 5 years | - |
| Traincrew | 19 | 3% | 11% | 1 a day, the least in 5 years | - |
| Stations | 11 | 2% | 3% | 0 a day, more than 2 of the other 4 years | - |
| Operations | 9 | 1% | 5% | 0 a day, more than 2 of the other 4 years | - |
| Operator, other | 138 | 20% | 7% | 5 a day, the least in 5 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| OG | Ice on conductor rail/OHLE | 132 |
| Q3 | NZ Pumps T | 123 |
| TT | Leaf fall Neutral | 121 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 27 |
| IB | Points failure (including no fault found) | 25 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 23 |
| IC | Track circuit failure (including no fault found) | 21 |
| OS | Late start or delays to Railhead Conditioning or Ghost Train due to its own activity and not in reaction to another incident | 19 |
| M0 | Confirmed train cab based safety system fault (including GSMR) | 17 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 17 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 3,672 |
| TT | Leaf fall Neutral | 1,422 |
| Q3 | NZ Pumps T | 1,233 |
| TG | Driver | 1,231 |
| IC | Track circuit failure (including no fault found) | 1,005 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 945 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 698 |
| IH | Power Supply And Distribution System Failure | 691 |
| IB | Points failure (including no fault found) | 662 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 623 |