Dalston Junction

DLJ Private railways route
CSV JSON

88 delay minutes

The biggest share (34%) of the delay picked up at Dalston Junction in the four weeks to 9 December 2023 came from how the network was run.

67% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power78%16%27
Weather and structures--7%-
Autumn--7%-
External--4%3
Network management3034%17%13
The operators' causes
Train faults910%16%24
Traincrew56%11%8
Stations910%3%32
Operations33%5%6
Operator, other2528%7%4

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 2 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
VBVandalism or theft14
OVFire or evacuation due to fire alarm of Network Rail buildings other than stations not due to vandalism13
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure11
M0Confirmed train cab based safety system fault (including GSMR)9
RBPassengers joining/alighting9
J0Telecom equipment radio failure (GSM-R)7
OSLate start or delays to Railhead Conditioning or Ghost Train due to its own activity and not in reaction to another incident6
TGDriver5
QAWTT schedule and or LTP Process including erroneous simplifiers4
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)4
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver788
MDTechnical failures below the solebar352
M8Technical failures above the Solebar317
M7Door and Door system faults232
IBPoints failure (including no fault found)221
RBPassengers joining/alighting215
J3Axle Counter Failure206
M0Confirmed train cab based safety system fault (including GSMR)160
OHARS / TMS / SARS software problem (excluding scheduling issues and technical failures)156
VHPassenger Communication cord, door egress or emergency train alarm operated155