Leaves on the Line

Driffield

DRF North & East route
CSV JSON

30 delay minutes

Most of the delay picked up at Driffield in the four weeks to 9 December 2023 came from problems at stations.

0% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures--7%-
Autumn--7%-
External--4%-
Network management--17%-
The operators' causes
Train faults--16%-
Traincrew--11%-
Stations30100%3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 5 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
RAStation Buildings and Facilities (incl Platforms)30
Since 2018
CodeWhat Network Rail loggedMinutes
IBPoints failure (including no fault found)160
JXMiscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains)114
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.63
FFFOC Diagramming or Rostering issue54
FWLate start/yard overtime not explained by Operator41
OUDelays not Investigated by Network Rail30
RAStation Buildings and Facilities (incl Platforms)30
M8Technical failures above the Solebar24
OSLate start or delays to Railhead Conditioning or Ghost Train due to its own activity and not in reaction to another incident17
FOTime Lost en-route believed to be operator cause and information required from Operator (Ops Responsibility)15