754 delay minutes
The biggest share (38%) of the delay picked up at Earlsfield in the four weeks to 9 December 2023 came from signal, points and power faults.
66% of these minutes were knock-on from something that happened elsewhere first. 98% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 162 | 21% | 8% | 6 a day, the most in 5 years | - |
| Signals, points and power | 283 | 38% | 16% | 10 a day, the most in 5 years | - |
| Weather and structures | - | - | 7% | 0 a day, the least in 5 years | - |
| Autumn | 4 | <1% | 7% | 0 a day, more than 2 of the other 4 years | - |
| External | - | - | 4% | 0 a day, the least in 5 years | - |
| Network management | 104 | 14% | 17% | 4 a day, more than 2 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 105 | 14% | 16% | 4 a day, more than 3 of the other 4 years | 2 |
| Traincrew | - | - | 11% | 0 a day, the least in 5 years | - |
| Stations | 76 | 10% | 3% | 3 a day, the most in 5 years | - |
| Operations | - | - | 5% | 0 a day, the least in 5 years | - |
| Operator, other | 21 | 3% | 7% | 1 a day, more than 1 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IC | Track circuit failure (including no fault found) | 277 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 141 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 98 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 68 |
| RY | Mishap - Station Operating causes | 35 |
| R8 | Delay at Station believed to be operator cause and information required from operator (Ops Responsibility) | 24 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 21 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 19 |
| T2 | Delay at unstaffed station to non-DOO train | 17 |
| I5 | Possession over-run from planned work | 9 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 2,139 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 1,537 |
| T2 | Delay at unstaffed station to non-DOO train | 1,450 |
| MD | Technical failures below the solebar | 1,443 |
| IC | Track circuit failure (including no fault found) | 1,323 |
| TG | Driver | 1,319 |
| IB | Points failure (including no fault found) | 1,169 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 1,129 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 1,090 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 907 |