Effingham Junction
333 delay minutes
The biggest share (29%) of the delay picked up at Effingham Junction in the four weeks to 9 December 2023 came from how the network was run.
62% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 8 | 2% | 8% | 0 a day, more than 1 of the other 4 years | - |
| Signals, points and power | 6 | 2% | 16% | 0 a day, the least in 5 years | 1 |
| Weather and structures | - | - | 7% | 0 a day, the least in 5 years | - |
| Autumn | 91 | 27% | 7% | 3 a day, more than 3 of the other 4 years | - |
| External | 5 | 2% | 4% | 0 a day, more than 3 of the other 4 years | - |
| Network management | 95 | 29% | 17% | 3 a day, more than 1 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 22 | 7% | 16% | 1 a day, more than 1 of the other 4 years | - |
| Traincrew | 7 | 2% | 11% | 0 a day, more than 1 of the other 4 years | - |
| Stations | 25 | 8% | 3% | 1 a day, more than 1 of the other 4 years | - |
| Operations | 8 | 2% | 5% | 0 a day, more than 2 of the other 4 years | - |
| Operator, other | 66 | 20% | 7% | 2 a day, more than 2 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| Q3 | NZ Pumps T | 61 |
| TT | Leaf fall Neutral | 61 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 56 |
| QH | Adhesion problems due to leaf contamination | 23 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 18 |
| I5 | Possession over-run from planned work | 14 |
| MD | Technical failures below the solebar | 11 |
| R5 | Station staff error - e.g wrong announcements misdirection | 8 |
| RD | Attaching/detaching/shunter/watering | 8 |
| RY | Mishap - Station Operating causes | 8 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 5,078 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 3,467 |
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 1,109 |
| IC | Track circuit failure (including no fault found) | 1,027 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 968 |
| TG | Driver | 967 |
| TT | Leaf fall Neutral | 872 |
| T2 | Delay at unstaffed station to non-DOO train | 705 |
| MD | Technical failures below the solebar | 570 |
| QA | WTT schedule and or LTP Process including erroneous simplifiers | 564 |