Leaves on the Line

Ely

ELY Anglia route
CSV JSON

1,693 delay minutes

The biggest share (26%) of the delay picked up at Ely in the four weeks to 9 December 2023 came from signal, points and power faults.

64% of these minutes were knock-on from something that happened elsewhere first. 87% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track18611%8% 7 a day, more than 1 of the other 4 years1
Signals, points and power43626%16% 16 a day, more than 3 of the other 4 years2
Weather and structures422%7% 2 a day, more than 3 of the other 4 years-
Autumn654%7% 2 a day, more than 3 of the other 4 years1
External674%4% 2 a day, more than 1 of the other 4 years2
Network management40124%17% 14 a day, the most in 5 years8
The operators' causes
Train faults25515%16% 9 a day, more than 3 of the other 4 years6
Traincrew533%11% 2 a day, the least in 5 years1
Stations463%3% 2 a day, the most in 5 years-
Operations352%5% 1 a day, the least in 5 years-
Operator, other1096%7% 4 a day, the most in 5 years2

Period by period

Delay minutes a day, period by period. Gridlines every 50 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure167
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.152
M8Technical failures above the Solebar123
ICTrack circuit failure (including no fault found)110
J5Infrastructure Asset fault reported but proven to be mistaken105
JLSafety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff)69
IKTelecom equipment failure (including no fault found)62
QJSpecial working for leaf-fall track circuit operation62
FWLate start/yard overtime not explained by Operator52
MDTechnical failures below the solebar50
Since 2018
CodeWhat Network Rail loggedMinutes
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.19,549
TGDriver5,386
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure3,437
ICTrack circuit failure (including no fault found)3,382
I1Overhead line/third rail defect2,974
IBPoints failure (including no fault found)2,812
M8Technical failures above the Solebar2,586
MDTechnical failures below the solebar2,532
MCDiesel Loco failure, defect, attention2,188
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles2,073