East Midlands Parkway
67 delay minutes
Most of the delay picked up at East Midlands Parkway in the four weeks to 9 December 2023 came from weather and structures.
69% of these minutes were knock-on from something that happened elsewhere first. 39% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | Trains cancelled |
|---|---|---|---|---|
| Network Rail's causes | ||||
| Track | - | - | 8% | - |
| Signals, points and power | - | - | 16% | - |
| Weather and structures | 41 | 61% | 7% | 1 |
| Autumn | - | - | 7% | - |
| External | - | - | 4% | - |
| Network management | 5 | 7% | 17% | - |
| The operators' causes | ||||
| Train faults | 17 | 25% | 16% | 1 |
| Traincrew | 5 | 7% | 11% | - |
| Stations | - | - | 3% | - |
| Operations | - | - | 5% | - |
| Operator, other | - | - | 7% | - |
Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| JK | Flooding not due to exceptional weather | 41 |
| M7 | Door and Door system faults | 17 |
| Q1 | Takeback Pumps | 5 |
| TG | Driver | 5 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| M8 | Technical failures above the Solebar | 107 |
| TG | Driver | 80 |
| TA | Train-crew/loco/stock/unit diagram issues | 57 |
| IB | Points failure (including no fault found) | 41 |
| JK | Flooding not due to exceptional weather | 41 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 31 |
| TZ | Other Passenger Train Operating Company causes | 28 |
| OK | Delay caused by Operating staff oversight, issues or absence (excluding signallers and Control) | 25 |
| I5 | Possession over-run from planned work | 22 |
| MD | Technical failures below the solebar | 21 |