Leaves on the Line

East Midlands Parkway

EMD East Midlands route
CSV JSON

67 delay minutes

Most of the delay picked up at East Midlands Parkway in the four weeks to 9 December 2023 came from weather and structures.

69% of these minutes were knock-on from something that happened elsewhere first. 39% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures4161%7%1
Autumn--7%-
External--4%-
Network management57%17%-
The operators' causes
Train faults1725%16%1
Traincrew57%11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
JKFlooding not due to exceptional weather41
M7Door and Door system faults17
Q1Takeback Pumps5
TGDriver5
Since 2018
CodeWhat Network Rail loggedMinutes
M8Technical failures above the Solebar107
TGDriver80
TATrain-crew/loco/stock/unit diagram issues57
IBPoints failure (including no fault found)41
JKFlooding not due to exceptional weather41
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail31
TZOther Passenger Train Operating Company causes28
OKDelay caused by Operating staff oversight, issues or absence (excluding signallers and Control)25
I5Possession over-run from planned work22
MDTechnical failures below the solebar21