1,682 delay minutes
The biggest share (16%) of the delay picked up at Earlestown in the four weeks to 9 December 2023 came from faulty trains.
68% of these minutes were knock-on from something that happened elsewhere first. 92% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 40 | 2% | 8% | 1 a day, the least in 5 years | - |
| Signals, points and power | 138 | 8% | 16% | 5 a day, more than 2 of the other 4 years | - |
| Weather and structures | 246 | 15% | 7% | 9 a day, more than 3 of the other 4 years | - |
| Autumn | 252 | 15% | 7% | 9 a day, the most in 5 years | - |
| External | 36 | 2% | 4% | 1 a day, more than 2 of the other 4 years | - |
| Network management | 203 | 12% | 17% | 7 a day, more than 2 of the other 4 years | 1 |
| The operators' causes | |||||
| Train faults | 264 | 16% | 16% | 9 a day, more than 2 of the other 4 years | - |
| Traincrew | 169 | 10% | 11% | 6 a day, more than 1 of the other 4 years | - |
| Stations | 70 | 4% | 3% | 3 a day, more than 2 of the other 4 years | - |
| Operations | 50 | 3% | 5% | 2 a day, the least in 5 years | - |
| Operator, other | 215 | 13% | 7% | 8 a day, more than 3 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 173 |
| Q3 | NZ Pumps T | 172 |
| TT | Leaf fall Neutral | 152 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 86 |
| TG | Driver | 85 |
| TH | (Senior) Conductor/Train Manager | 71 |
| OU | Delays not Investigated by Network Rail | 63 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 48 |
| QI | Cautioning due to railhead leaf contamination | 45 |
| MD | Technical failures below the solebar | 44 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 5,616 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 3,670 |
| MD | Technical failures below the solebar | 3,539 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 3,093 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 2,430 |
| TH | (Senior) Conductor/Train Manager | 2,200 |
| ZU | No Cause Identified After investigation by both Parties | 1,916 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 1,911 |
| RB | Passengers joining/alighting | 1,835 |
| M7 | Door and Door system faults | 1,828 |