Leaves on the Line

Evesham

EVE Western route
CSV JSON

806 delay minutes

The biggest share (30%) of the delay picked up at Evesham in the four weeks to 9 December 2023 came from signal, points and power faults.

47% of these minutes were knock-on from something that happened elsewhere first. 68% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track8911%8% 3 a day, more than 3 of the other 4 years-
Signals, points and power23930%16% 9 a day, the most in 5 years-
Weather and structures22428%7% 8 a day, more than 3 of the other 4 years-
Autumn5<1%7% 0 a day, the least in 5 years-
External8<1%4% 0 a day, more than 1 of the other 4 years-
Network management9011%17% 3 a day, more than 2 of the other 4 years-
The operators' causes
Train faults9211%16% 3 a day, more than 2 of the other 4 years-
Traincrew354%11% 1 a day, the most in 5 years1
Stations132%3% 0 a day, the least in 5 years-
Operations--5% 0 a day, the least in 5 years-
Operator, other121%7% 0 a day, the least in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)205
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles75
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.72
OUDelays not Investigated by Network Rail60
IBPoints failure (including no fault found)54
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure47
TGDriver32
IASignal failure (including no fault found)30
M8Technical failures above the Solebar29
MDTechnical failures below the solebar22
Since 2018
CodeWhat Network Rail loggedMinutes
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)4,217
MDTechnical failures below the solebar2,010
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.1,598
JHCritical Rail Temperature speeds, (other than buckled rails)1,580
TGDriver1,167
IBPoints failure (including no fault found)1,139
ZUNo Cause Identified After investigation by both Parties1,133
M7Door and Door system faults771
IESignalling Functional Power Supply Failure745
MNBrake and brake systems faults; including wheel flats where no other cause had been identified722