Fazakerley

FAZ North West route
CSV JSON

14 delay minutes

Most of the delay picked up at Fazakerley in the four weeks to 9 December 2023 came from weather and structures.

0% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures14100%7%1
Autumn--7%-
External--4%-
Network management--17%-
The operators' causes
Train faults--16%4
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail14
Since 2018
CodeWhat Network Rail loggedMinutes
MDTechnical failures below the solebar49
M7Door and Door system faults25
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail14
M8Technical failures above the Solebar13
TBTrain cancelled or delayed at Train Operators request10
M0Confirmed train cab based safety system fault (including GSMR)8
MTConfirmed train borne safety system faults (not cab based)6
Q1Takeback Pumps4
TGDriver4
OEFailure to lay Sandite or operate Railhead Conditioning train as programmed4