Leaves on the Line

Filey

FIL North & East route
CSV JSON

14 delay minutes

Most of the delay picked up at Filey in the four weeks to 9 December 2023 came from signal, points and power faults.

71% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power1071%16%1
Weather and structures--7%-
Autumn--7%-
External--4%-
Network management429%17%-
The operators' causes
Train faults--16%-
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles10
OUDelays not Investigated by Network Rail4
Since 2018
CodeWhat Network Rail loggedMinutes
JLSafety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff)123
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.79
MDTechnical failures below the solebar39
OUDelays not Investigated by Network Rail25
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail24
IBPoints failure (including no fault found)20
IESignalling Functional Power Supply Failure20
IISignalling lineside cable fault19
OLSignal Box not open during booked hours13
TZOther Passenger Train Operating Company causes12