Farnborough (Main)
4,438 delay minutes
The biggest share (37%) of the delay picked up at Farnborough (Main) in the four weeks to 9 December 2023 came from signal, points and power faults.
47% of these minutes were knock-on from something that happened elsewhere first. 97% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 186 | 4% | 8% | 7 a day, more than 2 of the other 4 years | - |
| Signals, points and power | 1,627 | 37% | 16% | 58 a day, more than 3 of the other 4 years | 2 |
| Weather and structures | 755 | 17% | 7% | 27 a day, the most in 5 years | 9 |
| Autumn | 476 | 11% | 7% | 17 a day, the most in 5 years | - |
| External | 62 | 1% | 4% | 2 a day, more than 1 of the other 4 years | - |
| Network management | 512 | 12% | 17% | 18 a day, more than 2 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 253 | 6% | 16% | 9 a day, more than 1 of the other 4 years | - |
| Traincrew | 120 | 3% | 11% | 4 a day, more than 2 of the other 4 years | - |
| Stations | 54 | 1% | 3% | 2 a day, more than 2 of the other 4 years | - |
| Operations | 63 | 1% | 5% | 2 a day, the most in 5 years | - |
| Operator, other | 331 | 7% | 7% | 12 a day, more than 3 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IB | Points failure (including no fault found) | 1,297 |
| JD | Structures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes) | 730 |
| Q3 | NZ Pumps T | 281 |
| TT | Leaf fall Neutral | 281 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 175 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 106 |
| QI | Cautioning due to railhead leaf contamination | 91 |
| MD | Technical failures below the solebar | 89 |
| IJ | AWS/ATP/TPWS/Train stop/On track equipment failure | 85 |
| II | Signalling lineside cable fault | 77 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IB | Points failure (including no fault found) | 7,303 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 6,790 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 6,244 |
| IC | Track circuit failure (including no fault found) | 4,240 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 4,155 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 3,444 |
| TG | Driver | 3,082 |
| JX | Miscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains) | 2,796 |
| MD | Technical failures below the solebar | 2,754 |
| X4 | Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions | 2,441 |