Leaves on the Line

Fareham

FRM Wessex route
CSV JSON

3,766 delay minutes

Most of the delay picked up at Fareham in the four weeks to 9 December 2023 came from signal, points and power faults.

43% of these minutes were knock-on from something that happened elsewhere first. 99% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track39210%8% 14 a day, the most in 5 years1
Signals, points and power1,97452%16% 71 a day, the most in 5 years12
Weather and structures7<1%7% 0 a day, the least in 5 years1
Autumn2176%7% 8 a day, more than 3 of the other 4 years-
External1845%4% 7 a day, the most in 5 years4
Network management2617%17% 9 a day, more than 1 of the other 4 years3
The operators' causes
Train faults3509%16% 13 a day, the most in 5 years2
Traincrew892%11% 3 a day, the least in 5 years6
Stations501%3% 2 a day, more than 3 of the other 4 years1
Operations33<1%5% 1 a day, more than 2 of the other 4 years2
Operator, other2096%7% 7 a day, more than 1 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 50 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
IISignalling lineside cable fault1,640
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.361
Q3NZ Pumps T191
TTLeaf fall Neutral191
MFEngineering non-technical delays associated with Engineering staff who are not based in an Engineering depot e.g. Cleaners163
XKNational Grid Power Failure - local area also affected (inc outage, surges, blips where working standby generator/UPS installed)147
IBPoints failure (including no fault found)144
I1Overhead line/third rail defect90
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)72
I5Possession over-run from planned work68
Since 2018
CodeWhat Network Rail loggedMinutes
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.8,360
IISignalling lineside cable fault5,010
TGDriver4,044
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)3,919
I4OHLE/third rail power supply failure or reduction3,021
ICTrack circuit failure (including no fault found)2,951
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)2,915
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure2,313
MDTechnical failures below the solebar1,893
JXMiscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains)1,838