Fareham
3,766 delay minutes
Most of the delay picked up at Fareham in the four weeks to 9 December 2023 came from signal, points and power faults.
43% of these minutes were knock-on from something that happened elsewhere first. 99% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 392 | 10% | 8% | 14 a day, the most in 5 years | 1 |
| Signals, points and power | 1,974 | 52% | 16% | 71 a day, the most in 5 years | 12 |
| Weather and structures | 7 | <1% | 7% | 0 a day, the least in 5 years | 1 |
| Autumn | 217 | 6% | 7% | 8 a day, more than 3 of the other 4 years | - |
| External | 184 | 5% | 4% | 7 a day, the most in 5 years | 4 |
| Network management | 261 | 7% | 17% | 9 a day, more than 1 of the other 4 years | 3 |
| The operators' causes | |||||
| Train faults | 350 | 9% | 16% | 13 a day, the most in 5 years | 2 |
| Traincrew | 89 | 2% | 11% | 3 a day, the least in 5 years | 6 |
| Stations | 50 | 1% | 3% | 2 a day, more than 3 of the other 4 years | 1 |
| Operations | 33 | <1% | 5% | 1 a day, more than 2 of the other 4 years | 2 |
| Operator, other | 209 | 6% | 7% | 7 a day, more than 1 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| II | Signalling lineside cable fault | 1,640 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 361 |
| Q3 | NZ Pumps T | 191 |
| TT | Leaf fall Neutral | 191 |
| MF | Engineering non-technical delays associated with Engineering staff who are not based in an Engineering depot e.g. Cleaners | 163 |
| XK | National Grid Power Failure - local area also affected (inc outage, surges, blips where working standby generator/UPS installed) | 147 |
| IB | Points failure (including no fault found) | 144 |
| I1 | Overhead line/third rail defect | 90 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 72 |
| I5 | Possession over-run from planned work | 68 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 8,360 |
| II | Signalling lineside cable fault | 5,010 |
| TG | Driver | 4,044 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 3,919 |
| I4 | OHLE/third rail power supply failure or reduction | 3,021 |
| IC | Track circuit failure (including no fault found) | 2,951 |
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 2,915 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 2,313 |
| MD | Technical failures below the solebar | 1,893 |
| JX | Miscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains) | 1,838 |