Greenbank
494 delay minutes
The biggest share (27%) of the delay picked up at Greenbank in the four weeks to 9 December 2023 came from other operator causes.
1% of these minutes were knock-on from something that happened elsewhere first. 53% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 14 | 3% | 8% | 1 a day, more than 3 of the other 4 years | - |
| Signals, points and power | 13 | 3% | 16% | 0 a day, the least in 5 years | - |
| Weather and structures | 3 | <1% | 7% | 0 a day, more than 2 of the other 4 years | - |
| Autumn | 121 | 24% | 7% | 4 a day, more than 2 of the other 4 years | - |
| External | 11 | 2% | 4% | 0 a day, more than 3 of the other 4 years | - |
| Network management | 68 | 14% | 17% | 2 a day, more than 3 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 49 | 10% | 16% | 2 a day, more than 3 of the other 4 years | 1 |
| Traincrew | 30 | 6% | 11% | 1 a day, the most in 5 years | - |
| Stations | 22 | 4% | 3% | 1 a day, more than 2 of the other 4 years | - |
| Operations | 29 | 6% | 5% | 1 a day, the most in 5 years | - |
| Operator, other | 135 | 27% | 7% | 5 a day, more than 3 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| Q3 | NZ Pumps T | 99 |
| TT | Leaf fall Neutral | 98 |
| OU | Delays not Investigated by Network Rail | 51 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 46 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 38 |
| TG | Driver | 30 |
| QI | Cautioning due to railhead leaf contamination | 22 |
| RB | Passengers joining/alighting | 16 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 14 |
| IP | Points failure caused by snow or frost where heaters are fitted but found to be not turned on, not operative or defective | 13 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| J3 | Axle Counter Failure | 1,707 |
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 1,042 |
| Q3 | NZ Pumps T | 984 |
| TT | Leaf fall Neutral | 837 |
| IC | Track circuit failure (including no fault found) | 743 |
| RB | Passengers joining/alighting | 718 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 580 |
| TH | (Senior) Conductor/Train Manager | 468 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 416 |
| MD | Technical failures below the solebar | 357 |