Greenford

GFD Western route
CSV JSON

294 delay minutes

The biggest share (35%) of the delay picked up at Greenford in the four weeks to 9 December 2023 came from the operators' own operations.

89% of these minutes were knock-on from something that happened elsewhere first. 89% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track6321%8% 2 a day, the most in 5 years1
Signals, points and power4114%16% 1 a day, more than 2 of the other 4 years6
Weather and structures31%7% 0 a day, more than 2 of the other 4 years-
Autumn41%7% 0 a day, the most in 5 years-
External--4% 0 a day, the least in 5 years-
Network management4515%17% 2 a day, more than 2 of the other 4 years4
The operators' causes
Train faults145%16% 1 a day, more than 1 of the other 4 years2
Traincrew103%11% 0 a day, more than 1 of the other 4 years10
Stations--3% 0 a day, the least in 5 years-
Operations10335%5% 4 a day, the most in 5 years2
Operator, other114%7% 0 a day, the most in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 5 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
TZOther Passenger Train Operating Company causes95
IRBroken/cracked/twisted/buckled/flawed rail53
J0Telecom equipment radio failure (GSM-R)28
I7Engineer's train late into, from or failed in possession23
IBPoints failure (including no fault found)13
OUDelays not Investigated by Network Rail11
TATrain-crew/loco/stock/unit diagram issues8
TGDriver7
ZUNo Cause Identified After investigation by both Parties7
M7Door and Door system faults6
Since 2018
CodeWhat Network Rail loggedMinutes
IBPoints failure (including no fault found)408
ICTrack circuit failure (including no fault found)399
MDTechnical failures below the solebar362
TGDriver361
OCSignaller including mis-routing (not ERTM /ETCS related)356
MNBrake and brake systems faults; including wheel flats where no other cause had been identified296
QAWTT schedule and or LTP Process including erroneous simplifiers257
JSCondition of Track TSR outside the Timetable Planning Rules233
ZYUnivestigated station overtime System Roll-up Only230
M7Door and Door system faults220