Gillingham (Dorset)
437 delay minutes
The biggest share (30%) of the delay picked up at Gillingham (Dorset) in the four weeks to 9 December 2023 came from how the network was run.
89% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 33 | 8% | 8% | 1 a day, more than 2 of the other 4 years | - |
| Signals, points and power | 57 | 13% | 16% | 2 a day, the least in 5 years | - |
| Weather and structures | - | - | 7% | 0 a day, the least in 5 years | - |
| Autumn | 62 | 14% | 7% | 2 a day, the least in 5 years | - |
| External | 35 | 8% | 4% | 1 a day, more than 1 of the other 4 years | - |
| Network management | 130 | 30% | 17% | 5 a day, the least in 5 years | - |
| The operators' causes | |||||
| Train faults | 23 | 5% | 16% | 1 a day, the least in 5 years | - |
| Traincrew | 42 | 10% | 11% | 2 a day, the least in 5 years | - |
| Stations | - | - | 3% | 0 a day, the least in 5 years | - |
| Operations | 3 | <1% | 5% | 0 a day, more than 2 of the other 4 years | 1 |
| Operator, other | 53 | 12% | 7% | 2 a day, more than 1 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| ON | Delays not properly investigated by Network Rail | 49 |
| TG | Driver | 42 |
| XP | BRIDGE HIT | 35 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 32 |
| QI | Cautioning due to railhead leaf contamination | 22 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 21 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 20 |
| Q3 | NZ Pumps T | 19 |
| TT | Leaf fall Neutral | 19 |
| ID | Level crossing faults and failure incl. barrow/foot crossings and crossing treadles | 18 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 3,604 |
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 3,053 |
| MD | Technical failures below the solebar | 2,280 |
| IC | Track circuit failure (including no fault found) | 1,778 |
| TG | Driver | 1,764 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 1,534 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 1,464 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 1,221 |
| IB | Points failure (including no fault found) | 1,200 |
| J3 | Axle Counter Failure | 1,128 |