Leaves on the Line

Guildford

GLD Wessex route
CSV JSON

3,263 delay minutes

The biggest share (24%) of the delay picked up at Guildford in the four weeks to 9 December 2023 came from signal, points and power faults.

71% of these minutes were knock-on from something that happened elsewhere first. 98% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track2096%8% 7 a day, more than 2 of the other 4 years6
Signals, points and power76824%16% 27 a day, the most in 5 years10
Weather and structures2267%7% 8 a day, the most in 5 years12
Autumn2427%7% 9 a day, more than 3 of the other 4 years-
External572%4% 2 a day, more than 2 of the other 4 years-
Network management59018%17% 21 a day, more than 1 of the other 4 years16
The operators' causes
Train faults41013%16% 15 a day, more than 3 of the other 4 years16
Traincrew46114%11% 16 a day, more than 3 of the other 4 years54
Stations492%3% 2 a day, more than 1 of the other 4 years-
Operations31<1%5% 1 a day, more than 1 of the other 4 years6
Operator, other2217%7% 8 a day, more than 1 of the other 4 years3

Period by period

Delay minutes a day, period by period. Gridlines every 100 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
IBPoints failure (including no fault found)637
TGDriver255
JDStructures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes)190
Q3NZ Pumps T164
TTLeaf fall Neutral164
I5Possession over-run from planned work155
TITraincrew rostering problem134
IRBroken/cracked/twisted/buckled/flawed rail110
MDTechnical failures below the solebar105
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)86
Since 2018
CodeWhat Network Rail loggedMinutes
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.24,639
TGDriver8,557
ICTrack circuit failure (including no fault found)6,701
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)6,074
IBPoints failure (including no fault found)5,887
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)5,480
MDTechnical failures below the solebar4,702
I5Possession over-run from planned work4,230
TH(Senior) Conductor/Train Manager3,854
JXMiscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains)3,525