Leaves on the Line

Greenhithe for Bluewater

GNH Kent route
CSV JSON

0 delay minutes

No delay was picked up at Greenhithe for Bluewater in the four weeks to 9 December 2023.

100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures--7%-
Autumn--7%-
External--4%-
Network management--17%-
The operators' causes
Train faults--16%-
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
Nothing logged.
Since 2018
CodeWhat Network Rail loggedMinutes
ICTrack circuit failure (including no fault found)60
VHPassenger Communication cord, door egress or emergency train alarm operated17
IRBroken/cracked/twisted/buckled/flawed rail10
I6Delays as a result of line blocks / track patrols (including late handback)10
TH(Senior) Conductor/Train Manager7
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)7
MNBrake and brake systems faults; including wheel flats where no other cause had been identified4
IQTrackside sign blown down, fallen over, missing, defective, mis-placed4
Q3NZ Pumps T2
TTLeaf fall Neutral1