Great Yarmouth
95 delay minutes
The biggest share (22%) of the delay picked up at Great Yarmouth in the four weeks to 9 December 2023 came from signal, points and power faults.
77% of these minutes were knock-on from something that happened elsewhere first. 93% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 8 | 8% | 8% | 0 a day, more than 2 of the other 4 years | - |
| Signals, points and power | 21 | 22% | 16% | 1 a day, more than 2 of the other 4 years | - |
| Weather and structures | 9 | 9% | 7% | 0 a day, more than 3 of the other 4 years | - |
| Autumn | 12 | 13% | 7% | 0 a day, more than 1 of the other 4 years | - |
| External | - | - | 4% | 0 a day, the least in 5 years | - |
| Network management | 4 | 4% | 17% | 0 a day, the least in 5 years | 2 |
| The operators' causes | |||||
| Train faults | 17 | 18% | 16% | 1 a day, more than 1 of the other 4 years | - |
| Traincrew | 7 | 7% | 11% | 0 a day, more than 2 of the other 4 years | - |
| Stations | 2 | 2% | 3% | 0 a day, more than 2 of the other 4 years | - |
| Operations | 12 | 13% | 5% | 0 a day, more than 3 of the other 4 years | - |
| Operator, other | 3 | 3% | 7% | 0 a day, more than 1 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| M0 | Confirmed train cab based safety system fault (including GSMR) | 17 |
| J3 | Axle Counter Failure | 11 |
| JK | Flooding not due to exceptional weather | 9 |
| QI | Cautioning due to railhead leaf contamination | 9 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 9 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 8 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 7 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 4 |
| TH | (Senior) Conductor/Train Manager | 4 |
| J0 | Telecom equipment radio failure (GSM-R) | 3 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MU | Depot operating problem | 860 |
| IK | Telecom equipment failure (including no fault found) | 843 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 794 |
| MD | Technical failures below the solebar | 672 |
| M8 | Technical failures above the Solebar | 567 |
| Q1 | Takeback Pumps | 554 |
| M7 | Door and Door system faults | 548 |
| DD | Technical Fleet Holding Code | 447 |
| TG | Driver | 439 |
| IB | Points failure (including no fault found) | 388 |