Leaves on the Line

Hayes & Harlington

HAY Western route
CSV JSON

1,436 delay minutes

The biggest share (37%) of the delay picked up at Hayes & Harlington in the four weeks to 9 December 2023 came from faulty trains.

70% of these minutes were knock-on from something that happened elsewhere first. 75% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track25418%8% 9 a day, the most in 5 years5
Signals, points and power13710%16% 5 a day, more than 1 of the other 4 years18
Weather and structures--7% 0 a day, the least in 5 years-
Autumn191%7% 1 a day, the most in 5 years-
External2<1%4% 0 a day, the least in 5 years-
Network management25017%17% 9 a day, the most in 5 years6
The operators' causes
Train faults53337%16% 19 a day, the most in 5 years37
Traincrew675%11% 2 a day, more than 3 of the other 4 years3
Stations--3% 0 a day, the least in 5 years-
Operations936%5% 3 a day, the most in 5 years9
Operator, other826%7% 3 a day, the most in 5 years7

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
M2Delay due to ATO / ETCS equipment415
IRBroken/cracked/twisted/buckled/flawed rail134
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.114
OUDelays not Investigated by Network Rail96
TXDelays incurred on non-Network Rail running lines or networks including London Underground (except fleet related delays)64
TGDriver55
M8Technical failures above the Solebar41
ICTrack circuit failure (including no fault found)40
IBPoints failure (including no fault found)38
IJAWS/ATP/TPWS/Train stop/On track equipment failure35
Since 2018
CodeWhat Network Rail loggedMinutes
M2Delay due to ATO / ETCS equipment2,511
I1Overhead line/third rail defect1,797
ICTrack circuit failure (including no fault found)1,614
TGDriver1,600
IBPoints failure (including no fault found)1,478
M8Technical failures above the Solebar1,225
VHPassenger Communication cord, door egress or emergency train alarm operated1,136
RZOther Station Operating causes1,019
M0Confirmed train cab based safety system fault (including GSMR)936
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.923