Hebden Bridge
2,200 delay minutes
The biggest share (47%) of the delay picked up at Hebden Bridge in the four weeks to 9 December 2023 came from autumn leaves.
68% of these minutes were knock-on from something that happened elsewhere first. 57% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 70 | 3% | 8% | 3 a day, more than 3 of the other 4 years | - |
| Signals, points and power | 197 | 9% | 16% | 7 a day, the most in 5 years | 3 |
| Weather and structures | 147 | 7% | 7% | 5 a day, more than 3 of the other 4 years | - |
| Autumn | 1,039 | 47% | 7% | 37 a day, the most in 5 years | - |
| External | 83 | 4% | 4% | 3 a day, the most in 5 years | - |
| Network management | 221 | 10% | 17% | 8 a day, the most in 5 years | 1 |
| The operators' causes | |||||
| Train faults | 157 | 7% | 16% | 6 a day, more than 3 of the other 4 years | - |
| Traincrew | 54 | 2% | 11% | 2 a day, more than 2 of the other 4 years | 3 |
| Stations | 42 | 2% | 3% | 2 a day, more than 2 of the other 4 years | - |
| Operations | 126 | 6% | 5% | 5 a day, the most in 5 years | - |
| Operator, other | 65 | 3% | 7% | 2 a day, more than 1 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| QJ | Special working for leaf-fall track circuit operation | 968 |
| OU | Delays not Investigated by Network Rail | 110 |
| IH | Power Supply And Distribution System Failure | 102 |
| OD | Delays due to National/Regional/Route Operations directives or Route Control decision or directive | 67 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 63 |
| TZ | Other Passenger Train Operating Company causes | 60 |
| Q3 | NZ Pumps T | 57 |
| J3 | Axle Counter Failure | 56 |
| M7 | Door and Door system faults | 53 |
| MD | Technical failures below the solebar | 53 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MD | Technical failures below the solebar | 2,336 |
| TG | Driver | 2,006 |
| QJ | Special working for leaf-fall track circuit operation | 1,298 |
| X2 | Severe flooding beyond that which could be mitigated on Network Rail infrastructure | 1,141 |
| Q3 | NZ Pumps T | 1,095 |
| M8 | Technical failures above the Solebar | 1,059 |
| MU | Depot operating problem | 983 |
| TT | Leaf fall Neutral | 879 |
| RC | re-booked assistance for a person with reduced mobility joining/alighting, | 807 |
| M7 | Door and Door system faults | 797 |