Hendon
80 delay minutes
The biggest share (43%) of the delay picked up at Hendon in the four weeks to 9 December 2023 came from how the network was run.
46% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | Trains cancelled |
|---|---|---|---|---|
| Network Rail's causes | ||||
| Track | - | - | 8% | - |
| Signals, points and power | 24 | 30% | 16% | 1 |
| Weather and structures | - | - | 7% | - |
| Autumn | - | - | 7% | - |
| External | - | - | 4% | - |
| Network management | 34 | 43% | 17% | 3 |
| The operators' causes | ||||
| Train faults | - | - | 16% | - |
| Traincrew | 22 | 28% | 11% | - |
| Stations | - | - | 3% | - |
| Operations | - | - | 5% | - |
| Operator, other | - | - | 7% | - |
Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| OK | Delay caused by Operating staff oversight, issues or absence (excluding signallers and Control) | 34 |
| TG | Driver | 22 |
| I1 | Overhead line/third rail defect | 18 |
| J3 | Axle Counter Failure | 6 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| M8 | Technical failures above the Solebar | 404 |
| TG | Driver | 353 |
| TI | Traincrew rostering problem | 212 |
| XP | BRIDGE HIT | 124 |
| IC | Track circuit failure (including no fault found) | 118 |
| IB | Points failure (including no fault found) | 110 |
| JX | Miscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains) | 95 |
| IE | Signalling Functional Power Supply Failure | 95 |
| MC | Diesel Loco failure, defect, attention | 94 |
| MD | Technical failures below the solebar | 94 |