Leaves on the Line

Hastings

HGS Kent route
CSV JSON

1,457 delay minutes

The biggest share (33%) of the delay picked up at Hastings in the four weeks to 9 December 2023 came from signal, points and power faults.

56% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track222%8% 1 a day, more than 2 of the other 4 years2
Signals, points and power47933%16% 17 a day, the most in 5 years10
Weather and structures9<1%7% 0 a day, more than 2 of the other 4 years2
Autumn27919%7% 10 a day, the most in 5 years3
External181%4% 1 a day, more than 3 of the other 4 years3
Network management28219%17% 10 a day, the most in 5 years65
The operators' causes
Train faults644%16% 2 a day, more than 1 of the other 4 years15
Traincrew1249%11% 4 a day, more than 3 of the other 4 years6
Stations7<1%3% 0 a day, more than 2 of the other 4 years-
Operations312%5% 1 a day, more than 1 of the other 4 years3
Operator, other14310%7% 5 a day, more than 3 of the other 4 years1

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
IGBlock failure372
QICautioning due to railhead leaf contamination234
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)87
TGDriver71
ODDelays due to National/Regional/Route Operations directives or Route Control decision or directive62
VHPassenger Communication cord, door egress or emergency train alarm operated55
JXMiscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains)51
M8Technical failures above the Solebar51
Q3NZ Pumps T45
TTLeaf fall Neutral45
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver3,978
ICTrack circuit failure (including no fault found)2,752
IBPoints failure (including no fault found)2,481
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.2,196
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)2,180
JXMiscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains)1,689
JPFailure to maintain vegetation within network boundaries in accordance with prevailing Network Rail standards1,644
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure1,331
MDTechnical failures below the solebar1,311
M0Confirmed train cab based safety system fault (including GSMR)1,219