Hammerton
1,055 delay minutes
The biggest share (18%) of the delay picked up at Hammerton in the four weeks to 9 December 2023 came from how the network was run.
81% of these minutes were knock-on from something that happened elsewhere first. 89% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 14 | 1% | 8% | 1 a day, the least in 5 years | - |
| Signals, points and power | 109 | 10% | 16% | 4 a day, the most in 5 years | - |
| Weather and structures | 70 | 7% | 7% | 3 a day, the most in 5 years | - |
| Autumn | 161 | 15% | 7% | 6 a day, more than 2 of the other 4 years | - |
| External | 55 | 5% | 4% | 2 a day, the most in 5 years | - |
| Network management | 187 | 18% | 17% | 7 a day, more than 3 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 164 | 16% | 16% | 6 a day, more than 3 of the other 4 years | - |
| Traincrew | 100 | 9% | 11% | 4 a day, more than 3 of the other 4 years | - |
| Stations | 8 | <1% | 3% | 0 a day, the least in 5 years | - |
| Operations | 26 | 2% | 5% | 1 a day, more than 1 of the other 4 years | - |
| Operator, other | 162 | 15% | 7% | 6 a day, more than 2 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| Q3 | NZ Pumps T | 130 |
| TT | Leaf fall Neutral | 122 |
| OU | Delays not Investigated by Network Rail | 105 |
| M8 | Technical failures above the Solebar | 85 |
| TG | Driver | 57 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 46 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 42 |
| XO | External trees, building or structures encroaching or falling onto network infrastructure (not weather or vandalism) | 41 |
| TH | (Senior) Conductor/Train Manager | 40 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 29 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MD | Technical failures below the solebar | 1,876 |
| TG | Driver | 1,862 |
| Q3 | NZ Pumps T | 1,514 |
| IG | Block failure | 1,356 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 1,323 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 1,290 |
| IB | Points failure (including no fault found) | 1,265 |
| TT | Leaf fall Neutral | 1,163 |
| IA | Signal failure (including no fault found) | 1,161 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 1,007 |