Leaves on the Line

Honiton

HON Wessex route
CSV JSON

1,825 delay minutes

The biggest share (34%) of the delay picked up at Honiton in the four weeks to 9 December 2023 came from signal, points and power faults.

73% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track22112%8% 8 a day, the most in 5 years-
Signals, points and power62634%16% 22 a day, the most in 5 years2
Weather and structures18310%7% 7 a day, more than 3 of the other 4 years-
Autumn1649%7% 6 a day, the least in 5 years-
External432%4% 2 a day, more than 1 of the other 4 years-
Network management24613%17% 9 a day, more than 2 of the other 4 years1
The operators' causes
Train faults1498%16% 5 a day, the most in 5 years1
Traincrew694%11% 2 a day, the least in 5 years-
Stations10<1%3% 0 a day, more than 1 of the other 4 years-
Operations251%5% 1 a day, more than 3 of the other 4 years-
Operator, other905%7% 3 a day, more than 1 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
ICTrack circuit failure (including no fault found)292
IBPoints failure (including no fault found)198
IRBroken/cracked/twisted/buckled/flawed rail146
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure136
Q3NZ Pumps T87
TTLeaf fall Neutral87
JKFlooding not due to exceptional weather73
MDTechnical failures below the solebar55
ONDelays not properly investigated by Network Rail55
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions53
Since 2018
CodeWhat Network Rail loggedMinutes
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)4,935
MDTechnical failures below the solebar3,048
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.2,272
TGDriver1,923
ICTrack circuit failure (including no fault found)1,911
IBPoints failure (including no fault found)1,706
J3Axle Counter Failure1,456
T2Delay at unstaffed station to non-DOO train1,392
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions1,235
OCSignaller including mis-routing (not ERTM /ETCS related)1,221