Hounslow
344 delay minutes
The biggest share (42%) of the delay picked up at Hounslow in the four weeks to 9 December 2023 came from how the network was run.
81% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 4 | 1% | 8% | 0 a day, more than 2 of the other 4 years | - |
| Signals, points and power | 23 | 7% | 16% | 1 a day, the least in 5 years | - |
| Weather and structures | - | - | 7% | 0 a day, the least in 5 years | - |
| Autumn | 15 | 4% | 7% | 1 a day, more than 2 of the other 4 years | - |
| External | - | - | 4% | 0 a day, the least in 5 years | - |
| Network management | 144 | 42% | 17% | 5 a day, more than 3 of the other 4 years | 1 |
| The operators' causes | |||||
| Train faults | 27 | 8% | 16% | 1 a day, the least in 5 years | - |
| Traincrew | 20 | 6% | 11% | 1 a day, more than 1 of the other 4 years | 4 |
| Stations | 77 | 22% | 3% | 3 a day, the most in 5 years | - |
| Operations | 17 | 5% | 5% | 1 a day, more than 3 of the other 4 years | - |
| Operator, other | 18 | 5% | 7% | 1 a day, the least in 5 years | 2 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| OK | Delay caused by Operating staff oversight, issues or absence (excluding signallers and Control) | 42 |
| T2 | Delay at unstaffed station to non-DOO train | 39 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 31 |
| I6 | Delays as a result of line blocks / track patrols (including late handback) | 26 |
| M7 | Door and Door system faults | 23 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 23 |
| RQ | Un-booked assistance for a person with reduced mobility joining/alighting, | 19 |
| TA | Train-crew/loco/stock/unit diagram issues | 17 |
| Q3 | NZ Pumps T | 11 |
| TT | Leaf fall Neutral | 11 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 2,713 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 1,637 |
| TG | Driver | 1,592 |
| T2 | Delay at unstaffed station to non-DOO train | 1,192 |
| IC | Track circuit failure (including no fault found) | 1,061 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 876 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 861 |
| TH | (Senior) Conductor/Train Manager | 762 |
| IB | Points failure (including no fault found) | 625 |
| TI | Traincrew rostering problem | 618 |