Leaves on the Line

Hartlepool

HPL North & East route
CSV JSON

312 delay minutes

The biggest share (23%) of the delay picked up at Hartlepool in the four weeks to 9 December 2023 came from how the network was run.

31% of these minutes were knock-on from something that happened elsewhere first. 99% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track52%8% 0 a day, more than 2 of the other 4 years-
Signals, points and power6922%16% 2 a day, the most in 5 years-
Weather and structures--7% 0 a day, the least in 5 years-
Autumn93%7% 0 a day, more than 2 of the other 4 years-
External103%4% 0 a day, more than 1 of the other 4 years-
Network management7123%17% 3 a day, the most in 5 years1
The operators' causes
Train faults7022%16% 3 a day, more than 2 of the other 4 years1
Traincrew3<1%11% 0 a day, the least in 5 years2
Stations4414%3% 2 a day, more than 2 of the other 4 years-
Operations217%5% 1 a day, more than 2 of the other 4 years-
Operator, other103%7% 0 a day, more than 1 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 5 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles60
M8Technical failures above the Solebar35
OUDelays not Investigated by Network Rail33
RCre-booked assistance for a person with reduced mobility joining/alighting,25
OHARS / TMS / SARS software problem (excluding scheduling issues and technical failures)24
RBPassengers joining/alighting17
TZOther Passenger Train Operating Company causes17
MDTechnical failures below the solebar12
IKTelecom equipment failure (including no fault found)9
MNBrake and brake systems faults; including wheel flats where no other cause had been identified8
Since 2018
CodeWhat Network Rail loggedMinutes
XRCable vandalism or theft973
MDTechnical failures below the solebar750
RBPassengers joining/alighting737
RCre-booked assistance for a person with reduced mobility joining/alighting,712
XPBRIDGE HIT493
OCSignaller including mis-routing (not ERTM /ETCS related)490
MNBrake and brake systems faults; including wheel flats where no other cause had been identified464
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure433
XLFire external to but directly affecting the network (incl. line blocks for emergency services attending off network incidents)426
J3Axle Counter Failure391