Leaves on the Line

Harwich International

HPQ Anglia route
CSV JSON

216 delay minutes

The biggest share (39%) of the delay picked up at Harwich International in the four weeks to 9 December 2023 came from signal, points and power faults.

47% of these minutes were knock-on from something that happened elsewhere first. 61% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track--8% 0 a day, the least in 5 years-
Signals, points and power8539%16% 3 a day, more than 3 of the other 4 years2
Weather and structures73%7% 0 a day, more than 3 of the other 4 years-
Autumn52%7% 0 a day, the least in 5 years-
External--4% 0 a day, the least in 5 years-
Network management136%17% 0 a day, the least in 5 years-
The operators' causes
Train faults73%16% 0 a day, the least in 5 years1
Traincrew--11% 0 a day, the least in 5 years-
Stations136%3% 0 a day, more than 2 of the other 4 years-
Operations8539%5% 3 a day, the most in 5 years3
Operator, other2<1%7% 0 a day, the least in 5 years-

Period by period

Delay minutes a day, period by period. Gridlines every 5 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)85
IJAWS/ATP/TPWS/Train stop/On track equipment failure72
RQUn-booked assistance for a person with reduced mobility joining/alighting,13
OSLate start or delays to Railhead Conditioning or Ghost Train due to its own activity and not in reaction to another incident10
ICTrack circuit failure (including no fault found)9
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)7
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles4
MUDepot operating problem4
MFEngineering non-technical delays associated with Engineering staff who are not based in an Engineering depot e.g. Cleaners3
QAWTT schedule and or LTP Process including erroneous simplifiers3
Since 2018
CodeWhat Network Rail loggedMinutes
OTOps Safety TSR implemented for sighting issues relating to foot crossings, level crossings or signals (Not vegetation caused)1,114
ICTrack circuit failure (including no fault found)573
RQUn-booked assistance for a person with reduced mobility joining/alighting,409
IBPoints failure (including no fault found)403
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.380
JLSafety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff)349
MDTechnical failures below the solebar331
TGDriver288
XDLevel Crossing Incidents including misuse and emergency services being prioritised over rail services222
JXMiscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains)211