Harold Wood
4 delay minutes
Most of the delay picked up at Harold Wood in the four weeks to 9 December 2023 came from the operators' own operations.
100% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | Trains cancelled |
|---|---|---|---|---|
| Network Rail's causes | ||||
| Track | - | - | 8% | - |
| Signals, points and power | - | - | 16% | - |
| Weather and structures | - | - | 7% | - |
| Autumn | - | - | 7% | - |
| External | - | - | 4% | - |
| Network management | - | - | 17% | - |
| The operators' causes | ||||
| Train faults | - | - | 16% | 1 |
| Traincrew | - | - | 11% | - |
| Stations | - | - | 3% | - |
| Operations | 4 | 100% | 5% | 1 |
| Operator, other | - | - | 7% | - |
Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TX | Delays incurred on non-Network Rail running lines or networks including London Underground (except fleet related delays) | 4 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IB | Points failure (including no fault found) | 27 |
| I5 | Possession over-run from planned work | 20 |
| TG | Driver | 14 |
| M0 | Confirmed train cab based safety system fault (including GSMR) | 7 |
| I1 | Overhead line/third rail defect | 7 |
| OS | Late start or delays to Railhead Conditioning or Ghost Train due to its own activity and not in reaction to another incident | 6 |
| I2 | AC/DC trip (including no fault or cause found) | 6 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 5 |
| IE | Signalling Functional Power Supply Failure | 5 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 4 |