Leaves on the Line

Harrington

HRR North West route
CSV JSON

40 delay minutes

Most of the delay picked up at Harrington in the four weeks to 9 December 2023 came from signal, points and power faults.

0% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power40100%16%-
Weather and structures--7%1
Autumn--7%-
External--4%-
Network management--17%2
The operators' causes
Train faults--16%2
Traincrew--11%1
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
IASignal failure (including no fault found)40
Since 2018
CodeWhat Network Rail loggedMinutes
IASignal failure (including no fault found)108
AKSafety Ins and mishaps(derailments, fire, chemical spill) in off n/w freight yard or terminal (inc private sdgs affecting FOC32
RCre-booked assistance for a person with reduced mobility joining/alighting,21
TGDriver14
ICTrack circuit failure (including no fault found)7
Q1Takeback Pumps6
TZOther Passenger Train Operating Company causes6