Helsby
1,305 delay minutes
The biggest share (39%) of the delay picked up at Helsby in the four weeks to 9 December 2023 came from weather and structures.
34% of these minutes were knock-on from something that happened elsewhere first. 94% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 55 | 4% | 8% | 2 a day, more than 2 of the other 4 years | - |
| Signals, points and power | 138 | 11% | 16% | 5 a day, more than 1 of the other 4 years | - |
| Weather and structures | 513 | 39% | 7% | 18 a day, the most in 5 years | - |
| Autumn | 80 | 6% | 7% | 3 a day, more than 2 of the other 4 years | - |
| External | - | - | 4% | 0 a day, the least in 5 years | - |
| Network management | 111 | 9% | 17% | 4 a day, more than 1 of the other 4 years | 2 |
| The operators' causes | |||||
| Train faults | 112 | 9% | 16% | 4 a day, more than 1 of the other 4 years | - |
| Traincrew | 120 | 9% | 11% | 4 a day, more than 3 of the other 4 years | 4 |
| Stations | 5 | <1% | 3% | 0 a day, the least in 5 years | - |
| Operations | 99 | 8% | 5% | 4 a day, more than 2 of the other 4 years | 1 |
| Operator, other | 73 | 6% | 7% | 3 a day, more than 1 of the other 4 years | 1 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| JD | Structures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes) | 489 |
| TG | Driver | 108 |
| TZ | Other Passenger Train Operating Company causes | 65 |
| Q3 | NZ Pumps T | 63 |
| TT | Leaf fall Neutral | 61 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 38 |
| IB | Points failure (including no fault found) | 37 |
| OU | Delays not Investigated by Network Rail | 37 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 35 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 34 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 2,783 |
| TG | Driver | 2,519 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 1,901 |
| MD | Technical failures below the solebar | 1,466 |
| TZ | Other Passenger Train Operating Company causes | 1,433 |
| IA | Signal failure (including no fault found) | 1,351 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 1,286 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 1,263 |
| T2 | Delay at unstaffed station to non-DOO train | 1,187 |
| IC | Track circuit failure (including no fault found) | 966 |