Most of the delay picked up at Ingatestone in the four weeks to 9 December 2023 came from how the network was run.

100% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures--7%-
Autumn--7%-
External--4%-
Network management3100%17%-
The operators' causes
Train faults--16%-
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other--7%2

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 2 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
OSLate start or delays to Railhead Conditioning or Ghost Train due to its own activity and not in reaction to another incident3
Since 2018
CodeWhat Network Rail loggedMinutes
MNBrake and brake systems faults; including wheel flats where no other cause had been identified133
MDTechnical failures below the solebar128
MBElectic Loco failure, defect, attention81
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure64
FHFOC Planning issue (not diagramming or rostering)63
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.62
TGDriver54
M8Technical failures above the Solebar50
QMTrain schedule/STP Process including erroneous simplifiers45
XPBRIDGE HIT43