Kirkham & Wesham
801 delay minutes
The biggest share (23%) of the delay picked up at Kirkham & Wesham in the four weeks to 9 December 2023 came from other operator causes.
57% of these minutes were knock-on from something that happened elsewhere first. 76% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 9 | 1% | 8% | 0 a day, the least in 5 years | - |
| Signals, points and power | 41 | 5% | 16% | 1 a day, the least in 5 years | - |
| Weather and structures | 65 | 8% | 7% | 2 a day, the most in 5 years | - |
| Autumn | 124 | 15% | 7% | 4 a day, the least in 5 years | - |
| External | 31 | 4% | 4% | 1 a day, more than 3 of the other 4 years | 1 |
| Network management | 116 | 14% | 17% | 4 a day, more than 2 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 86 | 11% | 16% | 3 a day, more than 1 of the other 4 years | - |
| Traincrew | 81 | 10% | 11% | 3 a day, the least in 5 years | - |
| Stations | 20 | 2% | 3% | 1 a day, the least in 5 years | - |
| Operations | 44 | 5% | 5% | 2 a day, the least in 5 years | - |
| Operator, other | 185 | 23% | 7% | 7 a day, more than 1 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| Q3 | NZ Pumps T | 110 |
| TT | Leaf fall Neutral | 94 |
| OU | Delays not Investigated by Network Rail | 80 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 62 |
| VE | Ticket irregularities or refusals to pay | 55 |
| TH | (Senior) Conductor/Train Manager | 49 |
| MD | Technical failures below the solebar | 35 |
| TG | Driver | 32 |
| IB | Points failure (including no fault found) | 31 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 24 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| RB | Passengers joining/alighting | 6,663 |
| TG | Driver | 4,781 |
| MD | Technical failures below the solebar | 3,127 |
| RC | re-booked assistance for a person with reduced mobility joining/alighting, | 2,708 |
| Q3 | NZ Pumps T | 2,493 |
| TT | Leaf fall Neutral | 1,953 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 1,630 |
| TZ | Other Passenger Train Operating Company causes | 1,475 |
| J3 | Axle Counter Failure | 1,466 |
| TH | (Senior) Conductor/Train Manager | 1,395 |