Loughborough (Leics)
1,238 delay minutes
The biggest share (21%) of the delay picked up at Loughborough (Leics) in the four weeks to 9 December 2023 came from weather and structures.
60% of these minutes were knock-on from something that happened elsewhere first. 82% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 65 | 5% | 8% | 2 a day, more than 2 of the other 4 years | - |
| Signals, points and power | 86 | 7% | 16% | 3 a day, more than 1 of the other 4 years | - |
| Weather and structures | 261 | 21% | 7% | 9 a day, the most in 5 years | 1 |
| Autumn | 109 | 9% | 7% | 4 a day, the most in 5 years | - |
| External | 18 | 1% | 4% | 1 a day, more than 2 of the other 4 years | - |
| Network management | 242 | 20% | 17% | 9 a day, more than 3 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 194 | 16% | 16% | 7 a day, the most in 5 years | 1 |
| Traincrew | 80 | 6% | 11% | 3 a day, more than 3 of the other 4 years | - |
| Stations | 59 | 5% | 3% | 2 a day, the most in 5 years | - |
| Operations | 19 | 2% | 5% | 1 a day, more than 1 of the other 4 years | - |
| Operator, other | 107 | 9% | 7% | 4 a day, more than 3 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| JK | Flooding not due to exceptional weather | 189 |
| MD | Technical failures below the solebar | 80 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 57 |
| QJ | Special working for leaf-fall track circuit operation | 42 |
| TG | Driver | 37 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 36 |
| Q3 | NZ Pumps T | 35 |
| FW | Late start/yard overtime not explained by Operator | 32 |
| QI | Cautioning due to railhead leaf contamination | 32 |
| I5 | Possession over-run from planned work | 30 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 1,851 |
| MD | Technical failures below the solebar | 1,809 |
| M8 | Technical failures above the Solebar | 1,767 |
| ZU | No Cause Identified After investigation by both Parties | 1,624 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 1,596 |
| IB | Points failure (including no fault found) | 1,557 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 1,502 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 1,496 |
| FW | Late start/yard overtime not explained by Operator | 997 |
| IC | Track circuit failure (including no fault found) | 976 |