Leamington Spa
1,419 delay minutes
The biggest share (22%) of the delay picked up at Leamington Spa in the four weeks to 9 December 2023 came from faulty trains.
62% of these minutes were knock-on from something that happened elsewhere first. 96% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 44 | 3% | 8% | 2 a day, the least in 5 years | - |
| Signals, points and power | 192 | 13% | 16% | 7 a day, more than 1 of the other 4 years | 1 |
| Weather and structures | 7 | <1% | 7% | 0 a day, the least in 5 years | - |
| Autumn | 92 | 6% | 7% | 3 a day, the most in 5 years | - |
| External | 50 | 4% | 4% | 2 a day, more than 2 of the other 4 years | 3 |
| Network management | 285 | 20% | 17% | 10 a day, more than 1 of the other 4 years | 15 |
| The operators' causes | |||||
| Train faults | 308 | 22% | 16% | 11 a day, more than 1 of the other 4 years | 3 |
| Traincrew | 139 | 10% | 11% | 5 a day, the least in 5 years | 66 |
| Stations | 111 | 8% | 3% | 4 a day, the most in 5 years | - |
| Operations | 33 | 2% | 5% | 1 a day, the least in 5 years | 2 |
| Operator, other | 159 | 11% | 7% | 6 a day, more than 2 of the other 4 years | 6 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| MD | Technical failures below the solebar | 132 |
| TG | Driver | 94 |
| I5 | Possession over-run from planned work | 84 |
| IB | Points failure (including no fault found) | 81 |
| MP | Rail / wheel interface, adhesion problems (including ice on the running rail) | 81 |
| RB | Passengers joining/alighting | 53 |
| Q3 | NZ Pumps T | 50 |
| XP | BRIDGE HIT | 49 |
| MT | Confirmed train borne safety system faults (not cab based) | 49 |
| JP | Failure to maintain vegetation within network boundaries in accordance with prevailing Network Rail standards | 48 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 8,204 |
| TG | Driver | 5,775 |
| MD | Technical failures below the solebar | 4,380 |
| MC | Diesel Loco failure, defect, attention | 3,999 |
| IB | Points failure (including no fault found) | 3,965 |
| J3 | Axle Counter Failure | 3,942 |
| M8 | Technical failures above the Solebar | 2,263 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 2,182 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 2,124 |
| IC | Track circuit failure (including no fault found) | 2,111 |