London Liverpool Street
3,019 delay minutes
The biggest share (22%) of the delay picked up at London Liverpool Street in the four weeks to 9 December 2023 came from how the network was run.
81% of these minutes were knock-on from something that happened elsewhere first. 98% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 178 | 6% | 8% | 6 a day, the least in 5 years | 5 |
| Signals, points and power | 580 | 19% | 16% | 21 a day, more than 1 of the other 4 years | 18 |
| Weather and structures | 31 | 1% | 7% | 1 a day, the least in 5 years | 1 |
| Autumn | 34 | 1% | 7% | 1 a day, more than 2 of the other 4 years | - |
| External | 436 | 14% | 4% | 16 a day, the most in 5 years | 29 |
| Network management | 679 | 22% | 17% | 24 a day, more than 1 of the other 4 years | 70 |
| The operators' causes | |||||
| Train faults | 384 | 13% | 16% | 14 a day, the least in 5 years | 21 |
| Traincrew | 127 | 4% | 11% | 5 a day, more than 1 of the other 4 years | 20 |
| Stations | 45 | 1% | 3% | 2 a day, more than 1 of the other 4 years | - |
| Operations | 86 | 3% | 5% | 3 a day, more than 2 of the other 4 years | 6 |
| Operator, other | 441 | 15% | 7% | 16 a day, more than 3 of the other 4 years | 10 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| I2 | AC/DC trip (including no fault or cause found) | 464 |
| XP | BRIDGE HIT | 392 |
| VH | Passenger Communication cord, door egress or emergency train alarm operated | 385 |
| I8 | Animal Strike or Incursion within the control of Network Rail | 246 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 176 |
| TG | Driver | 113 |
| M8 | Technical failures above the Solebar | 101 |
| I5 | Possession over-run from planned work | 99 |
| M7 | Door and Door system faults | 94 |
| J9 | Preventative Maintenance to the infrastructure in response to a Remote Condition Monitoring Alert | 87 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 17,230 |
| TG | Driver | 12,381 |
| MD | Technical failures below the solebar | 11,155 |
| IB | Points failure (including no fault found) | 10,678 |
| M8 | Technical failures above the Solebar | 10,486 |
| M7 | Door and Door system faults | 9,372 |
| M0 | Confirmed train cab based safety system fault (including GSMR) | 6,605 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 6,316 |
| IC | Track circuit failure (including no fault found) | 5,841 |
| MN | Brake and brake systems faults; including wheel flats where no other cause had been identified | 5,631 |