Luton
3,886 delay minutes
The biggest share (26%) of the delay picked up at Luton in the four weeks to 9 December 2023 came from how the network was run.
76% of these minutes were knock-on from something that happened elsewhere first. 82% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 466 | 12% | 8% | 17 a day, the most in 5 years | - |
| Signals, points and power | 903 | 23% | 16% | 32 a day, the most in 5 years | 1 |
| Weather and structures | 150 | 4% | 7% | 5 a day, the most in 5 years | 1 |
| Autumn | 155 | 4% | 7% | 6 a day, more than 2 of the other 4 years | - |
| External | 183 | 5% | 4% | 7 a day, more than 3 of the other 4 years | - |
| Network management | 1,007 | 26% | 17% | 36 a day, more than 3 of the other 4 years | 7 |
| The operators' causes | |||||
| Train faults | 328 | 8% | 16% | 12 a day, more than 2 of the other 4 years | 4 |
| Traincrew | 343 | 9% | 11% | 12 a day, more than 2 of the other 4 years | 17 |
| Stations | 82 | 2% | 3% | 3 a day, more than 3 of the other 4 years | - |
| Operations | 28 | <1% | 5% | 1 a day, the least in 5 years | 3 |
| Operator, other | 242 | 6% | 7% | 9 a day, more than 1 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IC | Track circuit failure (including no fault found) | 329 |
| TG | Driver | 278 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 266 |
| OK | Delay caused by Operating staff oversight, issues or absence (excluding signallers and Control) | 185 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 184 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 175 |
| M8 | Technical failures above the Solebar | 149 |
| J3 | Axle Counter Failure | 134 |
| JB | Reactionary Delay to 'P' coded TSRs | 122 |
| XB | Vandalism or theft (including the placing of objects on the line) | 118 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 20,550 |
| M8 | Technical failures above the Solebar | 12,439 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 7,336 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 6,458 |
| IC | Track circuit failure (including no fault found) | 6,169 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 5,727 |
| IB | Points failure (including no fault found) | 5,060 |
| IV | Cutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure) | 4,483 |
| IH | Power Supply And Distribution System Failure | 4,394 |
| TI | Traincrew rostering problem | 4,303 |