Metrocentre
863 delay minutes
The biggest share (16%) of the delay picked up at Metrocentre in the four weeks to 9 December 2023 came from faulty trains.
38% of these minutes were knock-on from something that happened elsewhere first. 87% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 115 | 13% | 8% | 4 a day, the most in 5 years | - |
| Signals, points and power | 49 | 6% | 16% | 2 a day, more than 2 of the other 4 years | - |
| Weather and structures | 98 | 11% | 7% | 4 a day, the most in 5 years | - |
| Autumn | 80 | 9% | 7% | 3 a day, more than 2 of the other 4 years | - |
| External | 10 | 1% | 4% | 0 a day, more than 1 of the other 4 years | - |
| Network management | 107 | 12% | 17% | 4 a day, the most in 5 years | 24 |
| The operators' causes | |||||
| Train faults | 139 | 16% | 16% | 5 a day, more than 3 of the other 4 years | - |
| Traincrew | 53 | 6% | 11% | 2 a day, the most in 5 years | 1 |
| Stations | 42 | 5% | 3% | 2 a day, more than 1 of the other 4 years | - |
| Operations | 77 | 9% | 5% | 3 a day, the most in 5 years | 3 |
| Operator, other | 93 | 11% | 7% | 3 a day, more than 2 of the other 4 years | 1 |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 115 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 98 |
| M0 | Confirmed train cab based safety system fault (including GSMR) | 82 |
| Q3 | NZ Pumps T | 77 |
| OU | Delays not Investigated by Network Rail | 74 |
| TZ | Other Passenger Train Operating Company causes | 74 |
| TT | Leaf fall Neutral | 69 |
| TG | Driver | 49 |
| M8 | Technical failures above the Solebar | 25 |
| RC | re-booked assistance for a person with reduced mobility joining/alighting, | 19 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 1,328 |
| XW | Severe weather not snow affecting infrastructure the responsibility of Network Rail | 1,060 |
| MD | Technical failures below the solebar | 956 |
| Q3 | NZ Pumps T | 909 |
| TT | Leaf fall Neutral | 794 |
| TZ | Other Passenger Train Operating Company causes | 789 |
| RB | Passengers joining/alighting | 715 |
| RC | re-booked assistance for a person with reduced mobility joining/alighting, | 637 |
| MS | Planned underpowered or shortformed service and or vehicle, incl. exam set swaps | 607 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 597 |