March
965 delay minutes
The biggest share (33%) of the delay picked up at March in the four weeks to 9 December 2023 came from how the network was run.
74% of these minutes were knock-on from something that happened elsewhere first. 93% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 121 | 13% | 8% | 4 a day, the least in 5 years | - |
| Signals, points and power | 141 | 15% | 16% | 5 a day, more than 1 of the other 4 years | - |
| Weather and structures | 22 | 2% | 7% | 1 a day, more than 3 of the other 4 years | - |
| Autumn | 87 | 9% | 7% | 3 a day, the most in 5 years | - |
| External | 72 | 7% | 4% | 3 a day, more than 3 of the other 4 years | - |
| Network management | 318 | 33% | 17% | 11 a day, the most in 5 years | - |
| The operators' causes | |||||
| Train faults | 89 | 9% | 16% | 3 a day, more than 1 of the other 4 years | - |
| Traincrew | 26 | 3% | 11% | 1 a day, the least in 5 years | - |
| Stations | 11 | 1% | 3% | 0 a day, more than 2 of the other 4 years | - |
| Operations | 3 | <1% | 5% | 0 a day, the least in 5 years | - |
| Operator, other | 76 | 8% | 7% | 3 a day, more than 3 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| J5 | Infrastructure Asset fault reported but proven to be mistaken | 99 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 91 |
| QJ | Special working for leaf-fall track circuit operation | 68 |
| JL | Safety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff) | 43 |
| IC | Track circuit failure (including no fault found) | 40 |
| XK | National Grid Power Failure - local area also affected (inc outage, surges, blips where working standby generator/UPS installed) | 36 |
| FW | Late start/yard overtime not explained by Operator | 30 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 30 |
| IR | Broken/cracked/twisted/buckled/flawed rail | 25 |
| M9 | Reported fleet equipment defect - no fault found | 25 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 25,678 |
| JS | Condition of Track TSR outside the Timetable Planning Rules | 14,886 |
| IA | Signal failure (including no fault found) | 5,493 |
| IC | Track circuit failure (including no fault found) | 4,854 |
| IF | Train Describer/Panel/ARS/SSI/TDM Remote Control failure | 2,052 |
| ID | Level crossing faults and failure incl. barrow/foot crossings and crossing treadles | 1,804 |
| JH | Critical Rail Temperature speeds, (other than buckled rails) | 1,760 |
| MC | Diesel Loco failure, defect, attention | 1,625 |
| MD | Technical failures below the solebar | 1,352 |
| JL | Safety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff) | 1,298 |