Leaves on the Line

March

MCH Anglia route
CSV JSON

965 delay minutes

The biggest share (33%) of the delay picked up at March in the four weeks to 9 December 2023 came from how the network was run.

74% of these minutes were knock-on from something that happened elsewhere first. 93% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track12113%8% 4 a day, the least in 5 years-
Signals, points and power14115%16% 5 a day, more than 1 of the other 4 years-
Weather and structures222%7% 1 a day, more than 3 of the other 4 years-
Autumn879%7% 3 a day, the most in 5 years-
External727%4% 3 a day, more than 3 of the other 4 years-
Network management31833%17% 11 a day, the most in 5 years-
The operators' causes
Train faults899%16% 3 a day, more than 1 of the other 4 years-
Traincrew263%11% 1 a day, the least in 5 years-
Stations111%3% 0 a day, more than 2 of the other 4 years-
Operations3<1%5% 0 a day, the least in 5 years-
Operator, other768%7% 3 a day, more than 3 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 50 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
J5Infrastructure Asset fault reported but proven to be mistaken99
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.91
QJSpecial working for leaf-fall track circuit operation68
JLSafety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff)43
ICTrack circuit failure (including no fault found)40
XKNational Grid Power Failure - local area also affected (inc outage, surges, blips where working standby generator/UPS installed)36
FWLate start/yard overtime not explained by Operator30
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure30
IRBroken/cracked/twisted/buckled/flawed rail25
M9Reported fleet equipment defect - no fault found25
Since 2018
CodeWhat Network Rail loggedMinutes
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.25,678
JSCondition of Track TSR outside the Timetable Planning Rules14,886
IASignal failure (including no fault found)5,493
ICTrack circuit failure (including no fault found)4,854
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure2,052
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles1,804
JHCritical Rail Temperature speeds, (other than buckled rails)1,760
MCDiesel Loco failure, defect, attention1,625
MDTechnical failures below the solebar1,352
JLSafety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff)1,298