Leaves on the Line

Merthyr Vale

MEV Cardiff Valleys route
CSV JSON

0 delay minutes

No delay was picked up at Merthyr Vale in the four weeks to 9 December 2023.

100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track--8%-
Signals, points and power--16%-
Weather and structures--7%-
Autumn--7%-
External--4%-
Network management--17%-
The operators' causes
Train faults--16%1
Traincrew--11%-
Stations--3%-
Operations--5%-
Operator, other--7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 1 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
Nothing logged.
Since 2018
CodeWhat Network Rail loggedMinutes
IBPoints failure (including no fault found)43
TGDriver39
XWSevere weather not snow affecting infrastructure the responsibility of Network Rail30
JLSafety related incident caused by maintenance or infrastructure staff oversight or error (not Operations staff)27
M7Door and Door system faults16
ICTrack circuit failure (including no fault found)15
J3Axle Counter Failure14
MDTechnical failures below the solebar13
JXMiscellaneous items on track including litter (not including leaves, result of vandalism, weather or fallen/thrown from trains)11
R5Station staff error - e.g wrong announcements misdirection11