Leaves on the Line

Manchester Airport

MIA North West route
CSV JSON

4,245 delay minutes

The biggest share (24%) of the delay picked up at Manchester Airport in the four weeks to 9 December 2023 came from faulty trains.

89% of these minutes were knock-on from something that happened elsewhere first. 83% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track902%8% 3 a day, more than 2 of the other 4 years1
Signals, points and power54713%16% 20 a day, more than 2 of the other 4 years2
Weather and structures46111%7% 16 a day, the most in 5 years16
Autumn3097%7% 11 a day, more than 3 of the other 4 years1
External2576%4% 9 a day, the most in 5 years-
Network management3749%17% 13 a day, more than 2 of the other 4 years30
The operators' causes
Train faults1,01424%16% 36 a day, more than 2 of the other 4 years28
Traincrew57213%11% 20 a day, more than 1 of the other 4 years70
Stations1333%3% 5 a day, more than 2 of the other 4 years-
Operations1874%5% 7 a day, more than 2 of the other 4 years3
Operator, other3027%7% 11 a day, more than 2 of the other 4 years5

Period by period

Delay minutes a day, period by period. Gridlines every 100 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
TGDriver312
TH(Senior) Conductor/Train Manager237
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure183
MSPlanned underpowered or shortformed service and or vehicle, incl. exam set swaps179
MTConfirmed train borne safety system faults (not cab based)165
Q3NZ Pumps T153
XPBRIDGE HIT150
MDTechnical failures below the solebar145
M1Confirmed Pantograph ADD, associated system faults, positive PANCHEX activations and train borne power switch over systems (AC)143
MNBrake and brake systems faults; including wheel flats where no other cause had been identified139
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver18,623
MDTechnical failures below the solebar9,914
M8Technical failures above the Solebar7,141
TH(Senior) Conductor/Train Manager6,492
MSPlanned underpowered or shortformed service and or vehicle, incl. exam set swaps6,039
M7Door and Door system faults5,859
MNBrake and brake systems faults; including wheel flats where no other cause had been identified4,852
IBPoints failure (including no fault found)4,713
IFTrain Describer/Panel/ARS/SSI/TDM Remote Control failure4,182
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)3,749