220 delay minutes

Most of the delay picked up at Moreton-in-Marsh in the four weeks to 9 December 2023 came from signal, points and power faults.

37% of these minutes were knock-on from something that happened elsewhere first. 98% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track105%8% 0 a day, more than 3 of the other 4 years-
Signals, points and power12456%16% 4 a day, more than 3 of the other 4 years-
Weather and structures42%7% 0 a day, more than 2 of the other 4 years-
Autumn31%7% 0 a day, more than 1 of the other 4 years-
External31%4% 0 a day, more than 2 of the other 4 years-
Network management3415%17% 1 a day, more than 1 of the other 4 years3
The operators' causes
Train faults178%16% 1 a day, the least in 5 years1
Traincrew199%11% 1 a day, more than 3 of the other 4 years-
Stations--3% 0 a day, the least in 5 years-
Operations31%5% 0 a day, more than 3 of the other 4 years-
Operator, other31%7% 0 a day, more than 1 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 10 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
IDLevel crossing faults and failure incl. barrow/foot crossings and crossing treadles72
IASignal failure (including no fault found)24
I8Animal Strike or Incursion within the control of Network Rail21
IISignalling lineside cable fault21
TGDriver13
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.10
MUDepot operating problem9
OUDelays not Investigated by Network Rail9
TITraincrew rostering problem6
MDTechnical failures below the solebar5
Since 2018
CodeWhat Network Rail loggedMinutes
MDTechnical failures below the solebar1,023
XPBRIDGE HIT669
M8Technical failures above the Solebar491
JDStructures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes)489
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.448
ZUNo Cause Identified After investigation by both Parties426
V8Train striking or being struck by a bird391
TGDriver358
M7Door and Door system faults354
X4Blanket speed restrictions or Key Route Strategy implemented with Group Standards or national operational safety instructions347