Mirfield
539 delay minutes
The biggest share (18%) of the delay picked up at Mirfield in the four weeks to 9 December 2023 came from how the network was run.
78% of these minutes were knock-on from something that happened elsewhere first. 93% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.
By cause
| Cause | Minutes | Share | Network-wide | A day, against the same period other years | Trains cancelled |
|---|---|---|---|---|---|
| Network Rail's causes | |||||
| Track | 37 | 7% | 8% | 1 a day, more than 3 of the other 4 years | - |
| Signals, points and power | 46 | 9% | 16% | 2 a day, more than 2 of the other 4 years | - |
| Weather and structures | 41 | 8% | 7% | 1 a day, the most in 5 years | - |
| Autumn | 92 | 17% | 7% | 3 a day, the most in 5 years | - |
| External | 40 | 7% | 4% | 1 a day, the most in 5 years | - |
| Network management | 99 | 18% | 17% | 4 a day, more than 2 of the other 4 years | - |
| The operators' causes | |||||
| Train faults | 59 | 11% | 16% | 2 a day, more than 2 of the other 4 years | - |
| Traincrew | 57 | 10% | 11% | 2 a day, more than 2 of the other 4 years | - |
| Stations | 12 | 2% | 3% | 0 a day, more than 2 of the other 4 years | - |
| Operations | 35 | 6% | 5% | 1 a day, the most in 5 years | - |
| Operator, other | 23 | 4% | 7% | 1 a day, more than 2 of the other 4 years | - |
Period by period
The codes behind it
| Code | What Network Rail logged | Minutes |
|---|---|---|
| QJ | Special working for leaf-fall track circuit operation | 73 |
| OU | Delays not Investigated by Network Rail | 54 |
| TG | Driver | 29 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 28 |
| TH | (Senior) Conductor/Train Manager | 26 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 20 |
| M8 | Technical failures above the Solebar | 19 |
| JD | Structures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes) | 18 |
| XP | BRIDGE HIT | 17 |
| TO | Time lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility) | 15 |
| Code | What Network Rail logged | Minutes |
|---|---|---|
| TG | Driver | 2,302 |
| QJ | Special working for leaf-fall track circuit operation | 1,494 |
| MD | Technical failures below the solebar | 1,225 |
| IS | Track defects (other than rail defects) inc. fish plates, wet beds etc. | 1,104 |
| TH | (Senior) Conductor/Train Manager | 962 |
| ZS | No Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties) | 749 |
| M7 | Door and Door system faults | 744 |
| M8 | Technical failures above the Solebar | 738 |
| OC | Signaller including mis-routing (not ERTM /ETCS related) | 627 |
| QA | WTT schedule and or LTP Process including erroneous simplifiers | 608 |