Leaves on the Line

Mirfield

MIR North & East route
CSV JSON

539 delay minutes

The biggest share (18%) of the delay picked up at Mirfield in the four weeks to 9 December 2023 came from how the network was run.

78% of these minutes were knock-on from something that happened elsewhere first. 93% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024, so they may still move.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track377%8% 1 a day, more than 3 of the other 4 years-
Signals, points and power469%16% 2 a day, more than 2 of the other 4 years-
Weather and structures418%7% 1 a day, the most in 5 years-
Autumn9217%7% 3 a day, the most in 5 years-
External407%4% 1 a day, the most in 5 years-
Network management9918%17% 4 a day, more than 2 of the other 4 years-
The operators' causes
Train faults5911%16% 2 a day, more than 2 of the other 4 years-
Traincrew5710%11% 2 a day, more than 2 of the other 4 years-
Stations122%3% 0 a day, more than 2 of the other 4 years-
Operations356%5% 1 a day, the most in 5 years-
Operator, other234%7% 1 a day, more than 2 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 20 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
QJSpecial working for leaf-fall track circuit operation73
OUDelays not Investigated by Network Rail54
TGDriver29
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.28
TH(Senior) Conductor/Train Manager26
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)20
M8Technical failures above the Solebar19
JDStructures - Bridges/tunnels/buildings/retaining walls/sea defences (not bridge strikes)18
XPBRIDGE HIT17
TOTime lost en-route believed to be Operator cause and information required form operatore (Ops Responsibility)15
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver2,302
QJSpecial working for leaf-fall track circuit operation1,494
MDTechnical failures below the solebar1,225
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.1,104
TH(Senior) Conductor/Train Manager962
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)749
M7Door and Door system faults744
M8Technical failures above the Solebar738
OCSignaller including mis-routing (not ERTM /ETCS related)627
QAWTT schedule and or LTP Process including erroneous simplifiers608