Melton Mowbray

MMO East Midlands route
CSV JSON

89 delay minutes

The biggest share (45%) of the delay picked up at Melton Mowbray in the four weeks to 9 December 2023 came from how the network was run.

96% of these minutes were knock-on from something that happened elsewhere first. 100% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideTrains cancelled
Network Rail's causes
Track1112%8%-
Signals, points and power--16%-
Weather and structures--7%1
Autumn1820%7%-
External--4%-
Network management4045%17%1
The operators' causes
Train faults56%16%-
Traincrew78%11%-
Stations--3%-
Operations--5%-
Operator, other910%7%-

Quiet enough here (under 100 delay minutes a period on average) that comparing years would mostly be noise, so there's no comparison.

Period by period

Delay minutes a day, period by period. Gridlines every 2 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
I5Possession over-run from planned work27
QICautioning due to railhead leaf contamination9
Q3NZ Pumps T9
JBReactionary Delay to 'P' coded TSRs7
MPRail / wheel interface, adhesion problems (including ice on the running rail)6
FETrain Crew not available including after rest5
MDTechnical failures below the solebar5
ZUNo Cause Identified After investigation by both Parties5
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.4
OKDelay caused by Operating staff oversight, issues or absence (excluding signallers and Control)4
Since 2018
CodeWhat Network Rail loggedMinutes
TGDriver159
JBReactionary Delay to 'P' coded TSRs153
OCSignaller including mis-routing (not ERTM /ETCS related)113
I5Possession over-run from planned work101
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.92
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)88
ICTrack circuit failure (including no fault found)85
IBPoints failure (including no fault found)80
TH(Senior) Conductor/Train Manager66
X2Severe flooding beyond that which could be mitigated on Network Rail infrastructure65