Leaves on the Line

Motspur Park

MOT Wessex route
CSV JSON

3,015 delay minutes

The biggest share (26%) of the delay picked up at Motspur Park in the four weeks to 9 December 2023 came from how the network was run.

74% of these minutes were knock-on from something that happened elsewhere first. 99% of them were agreed between Network Rail and the operators when the file came out on 5 Jan 2024.

By cause

Delay minutes by cause in 2023-24 P09
CauseMinutesShareNetwork-wideA day, against the same period other yearsTrains cancelled
Network Rail's causes
Track1655%8% 6 a day, more than 2 of the other 4 years-
Signals, points and power2428%16% 9 a day, more than 2 of the other 4 years-
Weather and structures21<1%7% 1 a day, more than 3 of the other 4 years-
Autumn64221%7% 23 a day, the most in 5 years-
External22<1%4% 1 a day, more than 2 of the other 4 years-
Network management79226%17% 28 a day, more than 3 of the other 4 years-
The operators' causes
Train faults1686%16% 6 a day, more than 2 of the other 4 years1
Traincrew1013%11% 4 a day, more than 2 of the other 4 years-
Stations1104%3% 4 a day, more than 1 of the other 4 years-
Operations--5% 0 a day, the least in 5 years-
Operator, other75225%7% 27 a day, more than 3 of the other 4 years-

Period by period

Delay minutes a day, period by period. Gridlines every 50 minutes. Hatched periods were under 94% agreed when their file came out, so they may still move. Pick a bar to see that period.

The codes behind it

In 2023-24 P09
CodeWhat Network Rail loggedMinutes
Q3NZ Pumps T612
TTLeaf fall Neutral612
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)470
ICTrack circuit failure (including no fault found)96
IRBroken/cracked/twisted/buckled/flawed rail92
IBPoints failure (including no fault found)91
OCSignaller including mis-routing (not ERTM /ETCS related)77
T2Delay at unstaffed station to non-DOO train73
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.71
OBDelayed by signaller not applying applicable regulating policy65
Since 2018
CodeWhat Network Rail loggedMinutes
ZSNo Cause ascertainable for a Sub-Threshold Delay causing Threshold Reactionary (where agreed by both parties)19,709
ISTrack defects (other than rail defects) inc. fish plates, wet beds etc.5,824
T2Delay at unstaffed station to non-DOO train4,896
TGDriver4,675
TTLeaf fall Neutral3,853
MDTechnical failures below the solebar3,334
IVCutting or embankment earthslip, rock fall or subsidence (not the result of severe weather on the day of failure)3,142
ICTrack circuit failure (including no fault found)3,135
OCSignaller including mis-routing (not ERTM /ETCS related)3,008
TH(Senior) Conductor/Train Manager2,802